Next Distribution
Centre

This 25-metre high distribution centre for Next spans 58,000m2. At one end of the steel structure is a five-storey office block. The centre is connected to an existing distribution centre on the other side of the road via a two-storey 120m link bridge. Although unusual, the bridge enables forklift trucks to carry goods between the two centres reducing the requirement for lorries to use local roads.

Next Distribution Centre project
Client Name
Bowmer & Kirkland
Sector
Retail and Leisure
Location
Doncaster
Duration
52 weeks

Project
Overview

By working closely with Bowmer & Kirkland on the drainage system, we were able to utilise two existing manholes and install the drainage at a depth of three metres rather than the planned eight metres, reducing the cost and time required for this part of the project.

The new structure also sits on 10,000 pile caps, of which 4,000 had flared heads and a tight tolerance.

Our Works
Included

  • Drainage
  • Pile cropping and flared heads
  • Attenuation systems and interceptor
  • Car park
  • Footways
  • External works and services
  • Foundations including those for the link bridge
  • CLSI pits
  • Concrete service yards
Next Distribution Centre construction work

Related Services

Learn more about the services behind our projects and delivery.

Earthworks, Site Preparation & Enabling Works

We deliver earthworks and site preparation, including bulk earthworks, earthmoving, soil remediation, site clearance, ground stabilisation, temporary works and enabling works.

Substructure & Reinforced Concrete

We provide specialist substructure, reinforced concrete and foundation works, from concrete walls, columns and slabs to industrial pits, formwork, transfer slabs and pump houses.

Drainage

We deliver complete drainage solutions, from surface, storm and foul water drainage to attenuation systems, culverts, pumping chambers and SuDS.