Chesterfield
Custody Suite
This project involves the delivery of a new custody suite for Derbyshire Constabulary in Chesterfield. The new 36-cell facility, located on Dunston Road, will provide modern, efficient services to support the Constabulary’s operational requirements.

- Client Name
- Willmott Dixon
- Sector
- Public Sector
- Location
- Chesterfield
- Duration
- 40 weeks

Project
Overview
The 4,732-square-metre development comprises of the custody suite, associated support facilities, site-wide ground improvements, drainage infrastructure, external works, and car parking. The project is scheduled for completion in June 2027.
Our Works
Included
- Cut and fill
- Substructures
- Site preparation works
- Roads, paths, pavings and surfacings
- Soft landscaping, planting
- External drainage
- External services

Related Services
Learn more about the services behind our projects and delivery.

Groundworks & External Works
We deliver comprehensive groundworks and external works, including excavation, foundations, piling, hard landscaping, kerbs, paving and external slabs.

Civil Engineering
We undertake a broad range of civil engineering works, including highways, S278 works, utility installations, road markings, sheet piling and retaining structures.