Trinity Academy St. Edward’s
Secondary School
A newbuild 900 pupil secondary school, consisting of a multi-storey teaching block with an adjacent sports hall, Multi Use Games Area (MUGA), synthetic sports pitch, grass playing fields and a 140-space car park.

- Client Name
- Bowmer & Kirkland
- Sector
- Education
- Location
- Barnsley
- Duration
- 44 weeks

Our Works
Included
- Pile caps foundations
- Ground floor slabs
- Drainage
- Attenuation tank
- Retaining wall foundations
- Services
- Kerbing
- Mine shaft capping
- Stone for hard landscaping areas
- Accompanying parking areas and access roads
Related Services
Learn more about the services behind our projects and delivery.

Groundworks & External Works
We deliver comprehensive groundworks and external works, including excavation, foundations, piling, hard landscaping, kerbs, paving and external slabs.

Civil Engineering
We undertake a broad range of civil engineering works, including highways, S278 works, utility installations, road markings, sheet piling and retaining structures.

Drainage
We deliver complete drainage solutions, from surface, storm and foul water drainage to attenuation systems, culverts, pumping chambers and SuDS.