The new 1500 place school and Sixth Form was constructed on the site of the existing school, modernising the buildings including a swimming pool and outdoor pitches.

- Client Name
- Bowmer & Kirkland
- Sector
- Education
- Location
- Coventry
- Duration
- 50 weeks

Project
Overview
Delivered via the ‘School Rebuilding Programme’, the school was part of the DfE’s Modern Methods of Construction Framework and is net zero carbon in operation.
Our Works
Included
- Earthworks
- Piling mat
- Substructure works
- Floor slabs
- External works
- Retaining walls
- Drainage
- Services

Related Services
Learn more about the services behind our projects and delivery.

Groundworks & External Works
We deliver comprehensive groundworks and external works, including excavation, foundations, piling, hard landscaping, kerbs, paving and external slabs.

Civil Engineering
We undertake a broad range of civil engineering works, including highways, S278 works, utility installations, road markings, sheet piling and retaining structures.

Drainage
We deliver complete drainage solutions, from surface, storm and foul water drainage to attenuation systems, culverts, pumping chambers and SuDS.