Heartlands Hospital

This project was to create a new pathology unit at Heartlands Hospital in Birmingham.

The works comprised of the construction of a three-storey insitu concrete frame and floors as well as groundworks. Access to the site was difficult so deliveries had to be planned around the working times of the hospital.

Details

Customer – Interserve

Duration – 28 weeks

Location – Birmingham

Our works included

  • Drainage
  • Sheet piled retaining wall with capping beam
  • Services
  • External works
  • Piled foundations
  • Pile caps and ground beams
  • Crane bases
  • Insitu concrete frame
  • Attenuation
  • Precast concrete stairs