Granby Road
Edlington

This project delivered 387 new, high quality, energy efficient semi-detached and detached houses in the former mining village of Edlington, near Doncaster in Yorkshire. The scheme includes affordable housing and public open spaces.

Granby Road, Edlington project
Client Name
Keepmoat
Sector
Residential
Location
Edlington
Duration
7 years
Granby Road, Edlington construction

Project
Overview

Working as principal contractor, we were responsible for overseeing the demolition contractor and establishing the site compound for the main contractor. We worked closely with Doncaster Council and Severn Trent inspectors to re-utilise the existing highway and repair drains on the 374-plot development for Keepmoat Corporate.

The levels to the final 182 plots were re-designed, which lead to an increase in the earthworks midway through the project. By providing additional resources, we were able to accelerate works and maintain the current programme.

Our Works
Included

  • 19,000m3 earthworks including the breaking out, crushing and removal of 3,000m3 rock
  • Groundworks to 374 plots
  • Roads and sewers to adoptable standards
  • 360m of drainage repairs, temporary connections, outfall works and land drainage
  • Carriageway realignment and Section 278 works
  • Footpaths, block paving and shared drives
  • Street lighting, service mains and individual services
  • Retaining and screen walls
  • External works
Granby Road, Edlington construction work

Related Services

Learn more about the services behind our projects and delivery.

Earthworks, Site Preparation & Enabling Works

We deliver earthworks and site preparation, including bulk earthworks, earthmoving, soil remediation, site clearance, ground stabilisation, temporary works and enabling works.

Substructure & Reinforced Concrete

We provide specialist substructure, reinforced concrete and foundation works, from concrete walls, columns and slabs to industrial pits, formwork, transfer slabs and pump houses.

Drainage

We deliver complete drainage solutions, from surface, storm and foul water drainage to attenuation systems, culverts, pumping chambers and SuDS.